Brief Description of Works
District
Moradabad
Scheme ID
4604805
Scheme Name
Bilakudan W/s Scheme
Village Covered
2
Original Scheme Year
2019
Amount (Lakh)
256.00
Retrofitting Year
0
Amount (Lakh)
0.00
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Repairing Work of boundary Wall, Approach Road, Water Recharge & Campus Development Work
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
1284
Pipe Line (Replacement)
1137
FHTC Existing
891
FHTC Repair
680
FHTC New
278
Status
Partially Functional > 70 lacs
Specific reason for increasing cost
Two villages are included under the scheme. Since the base year is 2025, the population has increased and with this increase in population, the demand for water has also increased. Due to the increase in water demand, the size of the pipeline has increased and hence some pipeline and drinking water house connections have been proposed.