Brief Description of Works
District
Moradabad
Scheme ID
4605005
Scheme Name
Barbara Mazra water supply scheme
Village Covered
1
Original Scheme Year
2013
Amount (Lakh)
517.48
Retrofitting Year
0
Amount (Lakh)
0.00
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Repairing Work of boundary Wall, Approach Road, Water Recharge & Campus Development Work
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
4062
Pipe Line (Replacement)
1970
FHTC Existing
1032
FHTC Repair
460
FHTC New
367
Status
Partially Functional > 70 lacs
Specific reason for increasing cost
Under the scheme, pipelines have not been laid in one hamlet. Due to population growth, pipelines have been extended, and pipelines are damaged at various locations. Consequently, new pipelines and the addition of some drinking water houses have been proposed.