Brief Description of Works
District
Budaun
Scheme ID
4753509
Scheme Name
KHEDA JALALPUR PUKHTA
Village Covered
1
Original Scheme Year
2015
Amount (Lakh)
797.91
Retrofitting Year
0
Amount (Lakh)
0.00
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
2
Boundary Wall and Campus Devp.
Yes
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
7000
Pipe Line (Replacement)
13000
FHTC Existing
1540
FHTC Repair
1060
FHTC New
1754
Status
Partially Functional > 70 lacs
Specific reason for increasing cost
Scheme covers 19 majras, all of them are scattered in approx 22 km radius. In this scheme 61.70 km pipeline was laid previously out of which 13 km pipeline is damaged, which needs to be replaced and 7 km pipeline extension is required. 1754 new FHTCs and 1060 FHTCs are proposed for repairing.