Brief Description of Works

District Bareilly
Scheme ID 4766902
Scheme Name Tisua water supply scheme
Village Covered 1
Original Scheme Year 2015
Amount (Lakh) 274.08
Retrofitting Year 2020
Amount (Lakh) 97.35
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 0
Boundary Wall and Campus Devp. 40 m boundary wall
Pump House (New) 0
Pump House (Repair) 0
Pipe Line (New) 0
Pipe Line (Replacement) 2
FHTC Existing 1410
FHTC Repair 365
FHTC New 221
Status Partially Functional > 70 lacs
Specific reason for increasing cost 5.982 km pipe line needs to relaced and newly laid. One habitation is on the other side of NH. So crossing of NH is also part of DPR. Boundary wall is also damagedin zone -2 of scheme. 365 connections need to be repaired and 221 no of new connections are also required.