Brief Description of Works
District
Unnao
Scheme ID
4827488
Scheme Name
BEHTA SUMHARI WSS
Village Covered
3
Original Scheme Year
2013
Amount (Lakh)
153.00
Retrofitting Year
2020
Amount (Lakh)
71.00
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
(Dismantling of existing Plaster & new plaster work, painting, etc.)
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
3529
Pipe Line (Replacement)
629
FHTC Existing
517
FHTC Repair
245
FHTC New
129
Status
Non-Functional > 100 lacs
Specific reason for increasing cost
1. Total existing pipeline of scheme is 9.31 km with respect to the requirement of 12.84 km as per present survey of OMIL to make the scheme fully functional.
2. Road dismantling & restoration of the 1.2 km required for pipe laying & new HSC.
3. Total existing FHTC found at site 517 with respect to the required 646 Household as per the present OMIL survey out of 517 FHTC, 245 FHTC are damaged condition need to repair. also, no of 129 new HSC is required to the fully functional.