Brief Description of Works
District
Unnao
Scheme ID
4827494
Scheme Name
KATRI PIPER KHERA WSS
Village Covered
1
Original Scheme Year
2014
Amount (Lakh)
191.58
Retrofitting Year
2020
Amount (Lakh)
41.28
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Dismantling of existing Plaster & new plaster work, painting
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
9752
Pipe Line (Replacement)
1295
FHTC Existing
342
FHTC Repair
76
FHTC New
178
Status
Non-Functional > 100 lacs
Specific reason for increasing cost
1. Total existing pipeline of scheme is 8.7 km with respect to the requirement of 16.87 km as per present survey of OMIL to make the scheme fully functional.
2. Road dismantling & restoration of the 3.5 km required for pipe laying & new HSC.
3. Total existing FHTC found at site 342 with respect to the required 520 Household as per the present OMIL survey out of 631 FHTC, 76 FHTC are damaged condition need to repair. also, no of 178 new HSC is required to the fully functional.
4. one no NHAI crossing (cost is 17 lac)