Brief Description of Works

District Unnao
Scheme ID 4827494
Scheme Name KATRI PIPER KHERA WSS
Village Covered 1
Original Scheme Year 2014
Amount (Lakh) 191.58
Retrofitting Year 2020
Amount (Lakh) 41.28
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Dismantling of existing Plaster & new plaster work, painting
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 9752
Pipe Line (Replacement) 1295
FHTC Existing 342
FHTC Repair 76
FHTC New 178
Status Non-Functional > 100 lacs
Specific reason for increasing cost 1. Total existing pipeline of scheme is 8.7 km with respect to the requirement of 16.87 km as per present survey of OMIL to make the scheme fully functional. 2. Road dismantling & restoration of the 3.5 km required for pipe laying & new HSC. 3. Total existing FHTC found at site 342 with respect to the required 520 Household as per the present OMIL survey out of 631 FHTC, 76 FHTC are damaged condition need to repair. also, no of 178 new HSC is required to the fully functional. 4. one no NHAI crossing (cost is 17 lac)