Brief Description of Works
District
Unnao
Scheme ID
4827498
Scheme Name
KULHA ATORA WSS
Village Covered
2
Original Scheme Year
2009
Amount (Lakh)
137.12
Retrofitting Year
2020
Amount (Lakh)
82.56
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Dismantling of existing Plaster & new plaster work, painting
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
16881
Pipe Line (Replacement)
0
FHTC Existing
83
FHTC Repair
58
FHTC New
726
Status
Non-Functional > 100 lacs
Specific reason for increasing cost
1. Total existing pipeline of scheme is 3.87 km with respect to the requirement of 20.75 km as per present survey of OMIL to make the scheme fully functional.
2. Road dismantling & restoration of the 5.08 km required for pipe laying & new HSC.
3. Total existing FHTC found at site 83 with respect to the required 809 Household as per the present OMIL survey out of 809 FHTC, 58 FHTC are damaged condition need to repair. also, no of 726 new HSC is required to the fully functional.
4. Existing pipe line designed for 4kg/cm2,working pressure as per old DPR