Brief Description of Works

District Unnao
Scheme ID 4827794
Scheme Name Pathakpur Water Supply scheme
Village Covered 1
Original Scheme Year 2013
Amount (Lakh) 157.38
Retrofitting Year 2020
Amount (Lakh) 62.08
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Dismantling of existing Plaster & new plaster work, painting
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 1718
Pipe Line (Replacement) 1228
FHTC Existing 455
FHTC Repair 148
FHTC New 195
Status Non-Functional > 100 lacs
Specific reason for increasing cost 1. Total existing pipeline of scheme is 9.24 km with respect to the requirement of 10.95 km as per present survey of OMIL to make the scheme fully functional. 2. Road dismantling & restoration of the 1.76 km required for pipe laying & new HSC. 3. Total existing FHTC found at site 455 with respect to the required 650 Household as per the present OMIL survey out of 650 FHTC, 148 FHTC are damaged condition need to repair. also, no of 195 new HSC is required to the fully functional. 4. One no FRU