Brief Description of Works
District
Raebareli
Scheme ID
484150
Scheme Name
BHITARI GRAM PANCHAYAT RURAL WATER SUPPLY SCHEME
Village Covered
1
Original Scheme Year
2015
Amount (Lakh)
183.52
Retrofitting Year
2020
Amount (Lakh)
48.04
New T/W
1
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Pump House (New)
1
Pump House (Repair)
0
Pipe Line (New)
2893
Pipe Line (Replacement)
3898
FHTC Existing
382
FHTC Repair
338
FHTC New
380
Status
Non-Functional > 100 lacs
Specific reason for increasing cost
1- This is a Non-functional scheme. In this scheme there is 1 revenue village & 5 habitations. 1 existing tubewell (grid based). Existing pipe material in this scheme is PVC.
2- We have proposed 6.791 km distribution pipe line in place of existing pipe line damaged due to construction of drain/nala/road etc. Inside the road due to road widing & change of dia of pipe line in respect of existing pipe line as per current hydraulic design.
3- Provision for construction of 1 new tubewell due to existing defunct tubewell with new campus.
4- Provision for construction of 380 new house connection due to increase of population & pending house hold, provision for repairing of 338 existing house connection due to damaged or non-functional.
5- Repairing of existing boundary wall such as di