Brief Description of Works

District Kannauj
Scheme ID 4866650
Scheme Name Singhpur Water Supply Scheme
Village Covered 1
Original Scheme Year 0
Amount (Lakh) 19.22
Retrofitting Year 0
Amount (Lakh) 38.85
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 0
Boundary Wall and Campus Devp.
Pump House (New) 0
Pump House (Repair) 0
Pipe Line (New) 0
Pipe Line (Replacement) 0
FHTC Existing 0
FHTC Repair 0
FHTC New 0
Status Fully Functional > 20 lacs
Specific reason for increasing cost THIS SCHEME IS CONSTRUCTED IN 2005 COVERED 7 HABITATION. THIS SCHEME IS CONSIDERED AS A FULLY FUNCTIONAL SCHEME IN THIS SCHEME 4 KG PVC WERE USED IN DISTRIBUTION NETWORK HAVING LENGTH 7075 METER. AS THE SCHEME IS OLD ALMOST ALL THE NETWORK ARE DAMAGED, WE ARE CONSIDERING ONLY 4600 MTR WE WILL ONLY REPAIR LEAKS, CARRY OUT JOINT, REPLACE/EXTEND PIPES. 2555 METER OF NEW LINE HAVE BEEN PROPOSED TO START REGULAR WATER SUPPLY TO EVERY HOUSE HOLD & 46 NEW FHTC ARE ALSO PROPOSED FOR NEWLY CONSTRUCTED HOUSE HOLD & 108 REPAIRING FHTC. THERE IS TWO PUMPHOUSE ARE THERE IN THE SCHEME ONE NEEDS ONLY REPAIR & TUBEWELL IS ALSO OK BUT FOR THE 2ND PUMP HOUSE THE NEW PUMP HOUSE & NEW TUBE WELL IS PROPOSED. CONDITION OF OHT IS ALSO VERY BAD MANY SEEPAGE ARE FOUND IN THE OHT SO WE CONSIDERED WATER PROOFING & P