Brief Description of Works
District
Ambedkar Nagar
Scheme ID
5042289
Scheme Name
Pakhkhanpur Water supply scheme
Village Covered
4
Original Scheme Year
2016
Amount (Lakh)
98.73
Retrofitting Year
2020
Amount (Lakh)
19.97
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Boundary wall and campus development work is proposed in DPR
Pump House (New)
0
Pump House (Repair)
5
Pipe Line (New)
5595
Pipe Line (Replacement)
6044
FHTC Existing
358
FHTC Repair
190
FHTC New
94
Status
Partially Functional > 70 lacs
Specific reason for increasing cost
1. The original scheme was constructed during the year 2016.
2. In retrofitting work 1.80 km pipe line and house connection work has been carried out under this scheme.
3 There are new developed habitation/household in discrete manner for which new pipe line is proposed, also in 3 RV of scheme water not reaches at household level as some existing pipe line are damaged and choked- so new design required. As per new design dia of pipe line changes, road dismantling and road restoration is also leading to increase the DPR cost.
4. other balance required works are proposed in this DPR
