Brief Description of Works
District
Sultanpur
Scheme ID
5055316
Scheme Name
Pratappur Kamaicha
Village Covered
1
Original Scheme Year
2010
Amount (Lakh)
0.00
Retrofitting Year
2021
Amount (Lakh)
0.00
New T/W
0
Rebore T/W
1
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
6078
Pipe Line (Replacement)
17410
FHTC Existing
265
FHTC Repair
140
FHTC New
1255
Status
Non-Functional > 100 lacs
Specific reason for increasing cost
1.As per the recent assessment of on-site conditions, approximately 20.2 km of 4 kg/cm² PVC pipeline was originally laid during the initial implementation phase (2010–11) to provide piped water supply coverage to one village and 7 habitations under a stand post-based design. During retrofitting works in 2020–21, an additional 1.9 km of 6 kg/cm² PVC pipeline (with diameters ranging from 63 mm to 110 mm) was laid, including 1.5 km of 63 mm PVC pipeline to improve system performance. However, the overall network length remained limited due to the original design being focused on stand posts, without adequate provision for household-level distribution. With the shift towards the Functional Household Tap Connection (FHTC) model, the revised design now mandates individual tap connections to all