Brief Description of Works

District Sant Ravidas Nagar
Scheme ID 5247067
Scheme Name Dasawatpur
Village Covered 1
Original Scheme Year 2008
Amount (Lakh) 39.92
Retrofitting Year 2020
Amount (Lakh) 76.41
New T/W 0
Rebore T/W 1
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. "Boundary wall: Provision for double priming coat with putty and double coat exterior emulsion paint. Campus development: No additional campus development works are necessary. Only the provision for internal square drain, including supply of all materials, labour, and T&P etc., complete in all respects, has been made. Provision has also been kept for a water recharge mechanism within the water works campus.
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 4512
Pipe Line (Replacement) 2257
FHTC Existing 454
FHTC Repair 327
FHTC New 217
Status Non-Functional > 100 lacs
Specific reason for increasing cost Under the Dasawatpur Water Supply Scheme, Block Abhauli, water supply to Dasawatpur village, covering 327 households, has been disrupted due to choked sections of the existing pipeline and damage caused during road widening works. The scheme is presently non-functional.To restore and improve the water supply, a total pipeline length of 6,769 meters has been proposed, which includes:Replacement of damaged sections of the existing pipeline along the road.Provision of new connections for recently constructed houses.Rehabilitation of choked and non-functional pipeline sections.The additional works required for repairing damaged pipelines, providing new household connections, and replacing non-functional and choked sections have resulted in an increase in the overall project cost.